- cripple public transport south of the Harbour
- create grid-lock in the arterial roads between the Eastern Suburbs and the rest of Sydney to the south and west
- create a killing field from Crown Street to George Street
- prevent the Northern Beaches from ever having effective public transport
- force Bankstown commuters onto a railway that does not connect anyone to anything
- require the privatisation of taxpayer assets that fund ongoing expenditure
Stage one
Establish express AM services between Liverpool, Cabramatta, Bankstown, Dulwich Hill, Sydenham, Redfern and Central stations.
- Cost: zero
- Rolling stock cost: zero
- Starting time: Immediately after 28th March 2015
Illawarra Junction |
Re-establish the connection between Bankstown and the inner-west line via Regents Park
- Cost: zero
- Rolling stock cost: zero
- Starting time: Immediately after 28th March 2015
Re-establish the connection between Cabramatta and Lidcombe via Regents Park
- Cost: zero
- Rolling stock cost: zero
- Starting time: Immediately after 28th March 2015
Use the Opal card to control peak-hour congestion in bus lanes in George Street
- Cost: zero
- Capital cost: zero
- Starting time: Immediately after 28th March 2015
Start work on preparing an Environmental Impact Statement for the restoration of the Pitt-Spring-Bent-Castlereagh Street tram loop
- Cost: zero
- Starting time: Immediately after 28th March 2015
Set up a Royal Commission into Transport for NSW
- Cost: Difficult to estimate
- Starting time: Immediately after 28th March 2015
The Royal Commission into Home Insulation cost $20 million and the Royal Commission into Julia Gillard's home renovations was to have cost $53 million but has blown out to $61 million. A Royal Commission into the incompetence and systemic deceit of public servants at Transport for NSW would have a lot of ground to cover:
Complete the Up and Down Illawarra relief rail
Start work on fly-under tunnels from main western lines to Central Terminal platforms and on underground platforms at Central Terminal.
The relief rail tunnel would dogleg under the RSL Club in George Street and Kent house in Liverpool Street and continue a leisured ascent under the Kent Street alignment to Wynyard station. The Iemma government passed legislation to protect potential rail alignments under the CBD - a property developer wanting to establish a basement deeper than 2 metres along the alignment had to obtain permission from the Rail Authority. The Kent Street alignment would need to be protected ASAP after 28th March 2015.
Restore the Pitt-Spring-Bent Castlereagh Streets tram loop
- Who exactly were the knutters at the Round Table discussions
- What were their qualifications
- What information were they given before taking part in the discussions
- How were decisions reached
- What information on costings did Baird have when he demanded a mandate to sell taxpayer electricity-distribution assets
- What work had been done on confirming the feasibility of a rail tunnel under the deepest part of the Harbour when Baird made his announcement
- What work had been done on locating and building stations under the "nominally Pitt Street" alignment when Baird made his announcement
- etc.
Stage two
Complete the Up and Down Illawarra relief rail
- Cost: Never been disclosed
- Rolling stock cost: Zero - Uses existing rolling stock more efficiently.
- Starting time: Shortly after 28th March 2015
Incomplete platform at St Peters station - aborted by North Shore anti-abortionists |
Start work on fly-under tunnels from main western lines to Central Terminal platforms and on underground platforms at Central Terminal.
- Cost: To be worked out
- Rolling stock cost: Zero - Uses existing rolling stock more efficiently
- Starting time: As soon as the design work has been done - takes place on railway land so should not require an EIS
The relief rail tunnel would dogleg under the RSL Club in George Street and Kent house in Liverpool Street and continue a leisured ascent under the Kent Street alignment to Wynyard station. The Iemma government passed legislation to protect potential rail alignments under the CBD - a property developer wanting to establish a basement deeper than 2 metres along the alignment had to obtain permission from the Rail Authority. The Kent Street alignment would need to be protected ASAP after 28th March 2015.
Restore the Pitt-Spring-Bent Castlereagh Streets tram loop
- Cost: To be worked out - less than half a billion dollars, say
- Cost of rolling stock: Zero - uses existing rolling stock on Dulwich Hill line more efficiently
- Starting date: In due course - after an EIS has been properly exhibited and properly assessed
Turn-back in the CBD
In order to reduce passenger loadings on the City Circle train services the number of train services transmogrifying from western/southern line services to Illawarra line services as they go round the loop must be reduced. The Airport/Wolli Creek line services must use the City Circle but alternative turn-backs can be built for western lines and Illawarra line peak services.
The obvious and least costly place in the CBD for turn-back to occur is under Belmore Park at Central station. For this to be feasible there must be a third rail loop to distribute passengers to destinations in the CBD north of Central. The George Street tram project was designed to obliterate all the places in the CBD where buses can physically turn around, crippling Parramatta and City Road public bus services among others. Modelling by consultants of TfNSW has conceded that it is not capable of distributing passengers from Central terminal to destinations in the CBD. The colonnade for the Pitt-Castlereagh Streets tram loop was built into the design of Central rail terminal and the loop fulfilled this function for more than 50 years. Restoration of the tram loop makes the Sydney CBD future proof, does not degrade any public bus or rail service and does not create grid-lock in vital arterial roads.
No comments:
Post a Comment